In force · As amended up to 2026-08
78. The detailed plan for conversion of each chemical weapons production facility shall contain:
- (a) Detailed time schedule of the conversion process;
- (b) Layout of the facility before and after conversion;
- (c) Process flow diagram of the facility before, and as appropriate, after the conversion;
- (d) Detailed inventory of equipment, buildings and structures and other items to be destroyed and
- of the buildings and structures to be modified;
- (e) Measures to be applied to each item on the inventory, if any;
- (f) Proposed measures for verification;
- (g) Security/safety measures to be observed during the conversion of the facility; and
- (h) Working and living conditions to be provided for inspectors.
Review of detailed plans
Source: India Code